GSICS Procedure for Product Acceptance (GPPA) Workflow

Related documents:
  • GSICS Procedure for Product Acceptance (GPPA), version 2.1 UPDATED
  • GSICS Product Acceptance Form (GPAF), version 1.2 UPDATED
  • GSICS Product External Review Form (GPERF), version 1.0 UPDATED
  • GPPA Checklist to document a product's progress through the GPPA

Skipping the Demo Phase

If an agency already has a correction product that has been through the submission phase of the GPPA and the same agency submits new products then these correction products can be accepted in the GPPA directly at the Pre-Op phase, if they satisfy some basic conditions. Please scroll below to learn more about these conditions under the 'GPPA For Family of Instruments' head.

Presented below are the GPPA Phases.

Product Submission Phase

  1. Fill out Sections I, II, III.1.A.1, and III.1.A.2 of the GSICS Product Acceptance Form (GPAF). Also, fill out Section III.1.B (ATBD) of the GPAF, but during the Submission Phase the ATBD needs only to be a preliminary version. The ATBD could be a journal article, technical memorandum or other documentation of the method used to make the product.
    • Who: Product provider
  2. Submit the GPAF and preliminary ATBD for review to the GSICS Product Acceptance Team (GPAT) via the GSICS Coordination Center (GCC) Deputy.
    • Who: Product provider
  3. Determine if the GPAF is filled out correctly and decide if the product theoretical basis is adequate and the product scope is within the GSICS domain.
    • Who: GPAT
    • Due: 6 weeks after the GPAF submission
  4. GPAT feedback given to the Product provider.
    • Who: GCC Director
    • Due: 7 weeks from GPAF submission
  5. Upload a sample file to a GSICS data server if GPAT feedback is affirmative.
    • Who: Product provider, GDWG Chairman
    • Due: One week after GPAT feedback regarding GPAF form submission
  6. Determine if the sample file follows the GSICS netCDF and file naming conventions.
    • Who: GDWG Chairman
    • Due: 2 weeks after successful product sample file upload
  7. Remediate any GPAF issues according to the GPAT feedback.
    • Who: Product provider, GCC Director
    • Due: Within 20 days after sending GPAT feedback to the Product provider
  8. Once all issues are resolved, the product enters the Demonstration Phase.
    • Who: GCC Director in consultation with the GPAT
    • Due: Within 90 days of the GPAF submission

Demonstration Phase

  1. Notify the Executive Panel about the Product entering Demonstration Phase.
    • Who: GCC Director
    • Due: Two weeks after the Product enters Demonstration Phase.
  2. Arrange for routine upload of the Product to a GSICS data server and agree on file retention policy.
    • Who: GDWG Chairman, GRWG Chairman, and Product provider
    • Due: One month after entering the Demonstration phase
  3. Notify GSICS users and invite feedback from them.
    • Who: GCC Director
    • Due: As soon as routine upload is completed and the file retention policy is resolved.
  4. Complete documents associated with GPAF Sections III.1.B (ATBD) and III.1.C (product traceability to standards) and submit them to the GCC Director.
    • Who: Product provider
    • Due: Three months after entering the Demonstration phase
  5. Examine the submitted documents (ATBD and product traceability to standards).
    • Who: GPAT and product users
    • Due: One month after GCC received the documents
  6. Remediate any document issues according to the GPAT and user feedback.
    • Who: Product provider, GCC Director
    • Due: One month after receiving GPAT feedback
  7. Complete documents associated with GPAF Sections III.2.A (radiative transfer models) and III.2.B (cal/val supporting measurements).
    • Who: Product provider
    • Due: Six months after entering the Demonstration phase
  8. Collect and disseminate user feedback regarding product's data usability and format
    • Who: Product users, GCC Director
    • Due: Six months after entering the Demonstration phase
  9. Examine the submitted documents (radiative transfer models and cal/val supporting measurements).
    • Who: GPAT
    • Due: One month after GCC received the documents
  10. Remediate any document or data issues according to the GPAT and user feedback.
    • Who: Product provider, GCC Director
    • Due: One month after receiving GPAT feedback
  11. [Major milestone] Make a consensus decision whether or not to continue the Product acceptance process.
    • Who: GPAT
    • Due: Two weeks after the remediation process ends for the documents regarding the radiative transfer models and cal/val supporting measurements
  12. Notify the Executive Panel on the status of the Product's acceptance process.
    • Who: GCC Director
    • Due: Two weeks following the GPAT decision on the Product's acceptance process.
  13. Complete and submit Section III.3.A (Product quality) of the GPAF.
    • Who: Product provider
    • Due: Ten months after entering the Demonstration phase
  14. Examine the submitted Product quality document.
    • Who: GPAT
    • Due: One month after GCC receives the document
  15. Remediate any document issues according to the GPAT feedback.
    • Who: Product provider, GCC Director
    • Due: One month after receiving GPAT feedback
  16. Once all issues are resolved, the Product enters the Pre-operational Phase.
    • Who: GCC Director in consultation with the GPAT
    • Due: Within one year of the product entering the Demonstration Phase

GPPA Exempt Clauses from Demo to Pre-Operational Phase ( and beyond)

1. If insufficient feedback is received from the beta-testers outside the GSICS algorithm development community during one year test period, GCC will make the suggestion to the EP based on the GPAT's review comments. The product provider(s) should systematically seek external feedback.

2. In case of incomplete documentation that are not considered to jeopardize product quality, GCC will make the suggestion to the EP based on the GPAT and users\x91 feedback. However, all the required documentations shall be completed and submitted for review purpose in the pre-operational phase.

GPPA Delegation Clause ( Accepted)

If a GPAT member wishes to deligate the review to a suitable reviewer ( within or outside the agency he belongs to) he/she can take the review and deligate review to the reviewer. The GPAT member still needs to oversee the review and ensure that the review is upto to expected standards.

The GCC, Product Producer, GPAT members needs to be informed deligation.

GPPA For Family of Instruments ( Accepted)

It is proposed that ...A correction NRT/RAC product can directly be accepted in the Pre-Op phase if

1. The product is created routinely

2. It follows the GSICS format ( filenaming and metadata )

3. The product is made from family of instruments that already create an existing data that has been accepted in the GSICS via the GPPA

Some of the examples are

GOES--13 Vs IASI-A product is already in Pre-Op stage in the GPPA. If one were to submit a GOES-16 Vs IASI-B in the same format as the GOES-13 -IASI-A then this product can be accepted in the pre-op phase directly. Any subset of this example is automatically accepted a product in Pre-Op. However it is upto the agency to provide information to the GCC to help the GCC Director use his descrition.

EP Recommendationa for GPPA

GWG.2016.2u.1 GCC to coordinate input from product creators/developers to identify the family of monitored and reference instruments their product is applicable to.

R.GCC.20180602.1 GCC to relax the requirement of User Guide for classical GSICS products

R.GCC.20180602.2 : GCC to relax the requirement of uncertainty analysis. This can be complimented by Impact Report showing impact of using Cross Calibration and due weighted should be given if Input L1B measurements are taken from Operational data processing streams of host agencies.

Pre-operational Phase

  1. Send notification and GPAT Product recommendations to the Executive Panel regarding the Product.
    • Who: GCC Director
    • Due: Two weeks after the Product enters the Pre-operational Phase.
  2. Executive Panel review of the GPAT recommendations. Executive Panel feedback regarding the product sent to the GCC Director.
    • Who: GSICS Executive Panel
    • Due: Six weeks after being notified
  3. GCC Director notifies the Product provider about the Executive Panel feedback.
    • Who: GCC Director
    • Due: Two weeks after receiving feedback from the Executive Panel
  4. Complete documents associated with GPAF Sections III.2.C (Analysis software documentation), III.2.D (Product version control plan), III.3.B (operations and distribution plan), and III.3.C (data user's guide) and submit the documents to the GCC.
    • Who: Product provider
    • Due: Three months after entering the Pre-operational phase
  5. Examine the submitted documents (product version control plan, operations and distribution plan, and data user's guide).
    • Who: GPAT
    • Due: One month after GCC received the documents
  6. Remediate any documentation and overall product issues following the Executive Panel and GPAT feedback.
    • Who: Product provider, GCC Director
    • Due: One month after receiving feedback
  7. GPAT reviews the remediation material and decides if the requirements are now satisfied. Sends final recommendation to the GCC Director.
    • Who: GPAT and GCC Director
    • Due: Thee weeks following conclusion of the document remediation period.
  8. GCC Director notifies the Executive Panel that the product has satisfied all the requirements for entering the Operational Phase.
    • Who: GCC Director
    • Due: One week following the GPAT review.

I Attachment Action Size Date Who Comment
GSICS_GCC_GPAF_V01.2.docdoc GSICS_GCC_GPAF_V01.2.doc manage 348 K 21 Jul 2011 - 13:14 RobertIacovazzi GSICS Product Acceptance Form
GSICS_GCC_GPAF_V01.3.docdoc GSICS_GCC_GPAF_V01.3.doc manage 349 K 17 Apr 2016 - 19:10 ManikBali New Contacts
GSICS_GCC_GPERF_V01.0.docdoc GSICS_GCC_GPERF_V01.0.doc manage 148 K 05 Jan 2011 - 13:49 RobertIacovazzi GSICS Product External Review Form
GSICS_GCC_GPPA_V02.1.pdfpdf GSICS_GCC_GPPA_V02.1.pdf manage 226 K 21 Jul 2011 - 13:21 RobertIacovazzi GSICS Procedure for Product Acceptance
GSICS_GCC_GPRF_V01.1.docdoc GSICS_GCC_GPRF_V01.1.doc manage 148 K 17 Apr 2016 - 19:28 ManikBali Review Form
This topic: Development > WebHome > GppaWorkflow
Topic revision: 30 Apr 2019, ManikBali
This site is powered by FoswikiCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding GSICS Wiki? Send feedback